This is a sample so you can see the format. Your plan is built around your own rooms, sizes and finishes, and priced for your area.
01 · Project summary and budget reality-check
Is your budget realistic?
You're planning a full renovation of a single main bathroom in an older double-brick home: strip it back to the brick and refit completely, with a freestanding bath, walk-in shower, wall-hung vanity and full floor-to-ceiling tiling.
For a mid-range bathroom of this size and scope in 2026, a realistic all-in figure sits in the range below. If your number is well under this, the quote is probably missing something. If it's well over, you may be paying for finishes above mid-range, or for access and structural issues specific to your home.
$16,000 to $19,500
Realistic all-in range for a licensed trade to do the full job, including materials and waterproofing. Indicative only.
This example is priced off a real completed Perth bathroom of this size and scope, not a generic market average. Labour and trade rates vary by city, so the same scope in Sydney or Melbourne can sit higher. Doing parts yourself, such as demolition, painting or fittings, reduces it further. Your own plan is priced for your area and for how much of the job you want to take on.
02 · Itemised budget
Where the money goes
| Item | Indicative |
| Strip-out and skip bin | $1,450 |
| Plumbing (rough-in and fit-off) | $2,780 |
| Electrical | $1,240 |
| Waterproofing to AS 3740 | $980 |
| Wall and floor tiling (supply and lay) | $3,760 |
| Vanity and benchtop | $1,980 |
| Bath, shower screen and toilet suite | $2,180 |
| Screed, plaster, paint and fittings | $3,305 |
| Indicative total | $17,675 |
These are the real final costs from a completed Perth bathroom of this size, using licensed trades for everything. This particular job ran without major surprises. Budget 10 to 15% on top as contingency when pricing your own job from a quote, more for a pre-1990 home where walls can hide problems.
03 · Build sequence
The right order, so nothing gets redone
- Asbestos check first. In a 1970s home, test before any demolition. This gates everything else.
- Strip-out and disposal. Remove fixtures, tiles and old waterproofing back to a sound substrate.
- Rough-in trades. Plumber and electrician set pipes and cabling for the new layout while walls are open.
- Plaster and make good. Patch and prepare wall surfaces.
- Screed and set falls. Floor graded to the drain before waterproofing.
- Waterproofing and cure. Applied to AS 3740, then left to cure fully. Do not rush this.
- Tiling. Floor and walls, only once waterproofing has cured.
- Cabinetry and benchtop. Vanity installed, benchtop templated and fitted after.
- Fit-off trades. Tapware, toilet, shower screen, lights, exhaust and heated rail.
- Paint, seal and clean. Final coats, silicone, detail and handover.
Order these early (long lead times): freestanding bath, tapware set, vanity and any special-order tiles. A late tile order is a common cause of a stalled bathroom.
04 · Compliance, permits and licensed trades
What has to be done by the book
WaterproofingMust comply with AS 3740. It is one of the most common failure points and one of the most expensive to fix later. Keep the certificate.
Licensed onlyPlumbing and electrical must be done by licensed trades, with certificates of compliance. Licensing is state-based, so use a trade licensed in your state. Do not accept cash-only unlicensed work here.
AsbestosPre-1990 homes may contain asbestos in wall sheeting or flooring. Test before you demolish. In WA, removing more than 10 m² of bonded asbestos, or any friable asbestos, needs a licensed removalist. Rules vary by state.
VentilationA compliant exhaust fan ducted to outside is required to meet the NCC and to prevent mould.
ApprovalsA like-for-like bathroom refit usually needs no planning approval, but confirm with your local council if you move walls or windows.
05 · Hidden-cost risks for this home
What tends to appear once the walls are open
- Old copper or galvanised pipework that needs replacing once exposed, common in 1970s homes.
- Rotten or damaged subfloor / substrate under the old waterproofing.
- Out-of-square walls and floors that slow tiling and add labour.
- Undersized or non-compliant wiring for modern heated rails and downlights.
- Asbestos in sheeting, which changes the demolition method and cost.
Each of these is why the 15% contingency is not optional on a home of this age.
06 · Commonly forgotten costs
The line items that blow budgets
Skip bin hire and disposal fees, temporary access to a second bathroom during the works, delivery charges on bath and tiles, protection of hallways and flooring, final builder's clean, and the price of tapware and tiles you fall in love with that sit above the allowance in a quote. Budget for these now, not as a nasty surprise later.
07 · What you can DIY vs must hire
You can do yourself
- Demolition of non-structural fittings
- Rubbish runs to the tip
- Painting
- Sourcing and buying fixtures
- Final clean
Must be a licensed trade
- Plumbing
- Electrical
- Waterproofing (certified or licensed installer, depending on your state)
- Structural changes
- Asbestos removal
08 · How to compare builder quotes
Is one quote actually cheaper, or just missing things?
- Is waterproofing listed as a separate, certified line, or buried and vague?
- Are tiles and tapware a real allowance, or a low placeholder you'll blow past?
- Is rubbish removal and skip hire included, or extra?
- Does it name the licensed plumber and electrician?
- Is there a contingency, or does the quote pretend nothing will go wrong?
- Are start and finish dates, and a payment schedule, written down?
A quote that is $3,000 cheaper but silent on three of these is usually not cheaper. It's incomplete.
This plan is indicative planning guidance to help you brief licensed trades and designers. It is an estimate, not a quote or fixed price, and not construction documentation, engineering, financial or legal advice. Costs and requirements vary, so always confirm scope, pricing, permits and compliance with appropriately licensed and registered professionals before committing money or starting work. © Renova Industries Pty Ltd.